Shear Studs & Welding Studs
Product code — to be assigned
Headed studs welded through the decking to make the steel beam and concrete slab act as one composite section.
- Headed stud with matched ceramic ferrule
- Drawn-arc welding through decking
- Batched by welding shift for bend testing
- Shank diameter
- Ø10 – Ø22 (confirm per design)
- Head diameter
- Per GB/T 10433 for the shank size
- Welded length
- To the composite design
- Material
- ML15 / ML15Al drawing-quality carbon steel
Quoting from Handan, Hebei Province, China. Reply capacity depends on the completeness of the specification supplied with the enquiry.
Product information
A shear stud carries the horizontal shear between a steel beam and the concrete slab cast on top of it. The stud is welded through the decking by a drawn-arc process, with a ceramic ferrule holding the weld pool and keeping the atmosphere out until the metal solidifies.
Shank diameter, head diameter and welded length come from the composite design, and the ferrule is matched to the stud diameter. Where the deck is profiled, the welded length is set against the rib geometry rather than the plain slab thickness.
Typical applications
- Composite beam and slab connection
- Steel deck through-welding
- Secondary composite floor framing
Packing & delivery
- Boxed by diameter, ferrules in the same carton
- Quantity and diameter on the label
- Palletized cartons for export
Customization (confirmed per order)
- Welded length to the deck profile
- Shank diameter to the composite design
- Batched by welding shift for sampling
Material & finish
- Material
- ML15 · ML15Al
- Finish
- Plain (as supplied for welding)
- Standard reference
- Dimensions follow GB/T 10433. Weld procedure and the bending test regime are agreed with the fabricator before the first delivery; no approval is claimed on this page.
Frequently asked questions
Are the ferrules included?
Yes, matched to the stud diameter and packed in the same carton, so the two cannot be separated on site.
Is a bending test required?
Normally yes — the fabricator bends a sample from the start of each welding shift. The acceptance angle is set by the project specification, not by the stud supplier.
Request a quotation
The product name is already attached to this form. Add the dimensions, quantity, material and finish required, and attach a drawing if one exists.
- tangtiemetal@163.com
- Phone / WhatsApp
- +86 16619861146
- Location
- Handan, Hebei Province, China